• Home
  • About
  • Contact
  • December 30, 2020
  • January 11, 2021
  • January 25, 2021
  • February 8, 2021
  • Past Installments
    • 2015 >
      • July 5, 2015
      • July 12, 2015
      • July 19, 2015
      • July 26, 2015
      • August 2, 2015
      • August 9, 2015
      • August 16, 2015
      • August 23, 2015
      • August 31, 2015
      • September 6, 2015
      • September 13, 2015
      • September 20, 2015
      • September 27, 2015
      • October 4, 2015
      • October 11, 2015
      • October 18, 2015
      • October 25, 2015
      • November 1, 2015
      • November 8, 2015
      • November 15, 2015
      • November 29, 2015
      • December 6, 2015
      • December 13, 2015
      • December 20, 2015
    • 2016 >
      • January 10, 2016
      • January 17, 2016
      • January 24, 2016
      • January 31, 2016
      • February 7, 2016
      • February 14, 2016
      • February 21, 2016
      • February 28, 2016
      • March 6, 2016
      • March 13, 2016
      • March 20, 2016
      • March 27, 2016
      • April 3, 2016
      • April 10, 2016
      • April 17, 2016
      • April 24, 2016
      • May 1, 2016
      • May 8, 2016
      • May 15, 2016
      • May 22, 2016
      • May 30, 2016
      • June 5, 2016
      • June 12 and 19
      • June 26 to July 3
      • July 24, 2016
      • July 31, 2016
      • August 7, 2016
      • August 14, 2016
      • August 21, 2016
      • August 28, 2016
      • September 4, 2016
      • September 11, 2016
      • September 18, 2016
      • September 25, 2016
      • October 2, 2106
      • October 9, 2016
      • October 16, 2016
      • October 23, 2016
      • October 30, 2016
      • November 6, 2016
      • November 13, 2016
      • November 27, 2016
      • December 4, 2016
      • December 11, 2016
      • December 19, 2016
    • 2017 >
      • Facilities Options
      • January 8, 2017
      • January 15, 2017
      • January 22, 2017
      • February 12, 2017
      • February 26, 2017
      • March 5, 2017
      • March 12, 2017
      • Spring Break 2017
      • April Fools
      • April 9, 2017
      • April 16, 2017
      • April 30, 2017
      • May 7, 2017
      • May 14, 2017
      • May 29, 2017
      • June 4, 2017
      • June 11, 2017
      • June 18, 2017
      • June 25, 2017
      • July 2, 2017
      • July 9, 2017
      • July 16, 2017
      • July 23, 2017
      • July 30, 2017
      • August 6, 2017
      • August 13, 2017
      • August 20, 2017
      • August 27, 2017
      • September 3, 2017
      • September 10, 2017
      • September 17, 2017
      • September 24, 2017
      • October 1, 2017
      • October 8, 2017
      • October 15, 2017
      • October 22, 2017
      • October 29, 2017
      • November 5, 2017
      • November 12, 2017
      • November 26, 2017
      • December 3, 2017
      • December 10, 2017
      • December 13, 2017
    • 2018 >
      • January 7, 2018
      • January 14, 2018
      • January 21, 2018
      • January 28, 2018
      • February 4, 2018
      • February 11, 2018
      • February 18, 2018
      • February 25, 2018
      • March 4, 2018
      • March 11, 2018
      • March 18, 2018
      • March 25, 2018
      • April 2, 2018
      • April 8, 2018
      • April 15, 2018
      • April 22, 2018
      • April 29, 2018
      • May 6, 2018
      • May 13, 2018
      • May 20, 2018
      • May 27, 2018
      • June 3, 2018
      • June 10, 2018
      • June 17, 2018
      • June 24, 2018
      • July 1, 2018
      • July 8, 2018
      • July 15, 2018
      • July 22, 2018
      • July 29, 2018
      • August 5, 2018
      • August 12, 2018
      • August 19, 2018
      • August 26, 2018
      • September 2, 2018
      • September 9, 2018
      • September 16. 2018
      • September 23, 2018
      • September 30, 2018
      • October 7, 2018
      • October 14, 2018
      • October 21, 2018
      • October 28, 2018
      • November 4, 2018
      • November 11, 2018
      • November 18, 2018
      • November 25, 2018
      • December 2, 2018
      • December 9, 2018
      • December 16, 2018
    • 2019 >
      • January 6, 2019
      • January 13, 2019
      • January 21, 2019
      • January 27, 2019
      • February 3, 2019
      • February 10, 2019
      • February 17, 2019
      • February 24, 2019
      • March 3, 2019
      • March 10, 2019
      • March 17, 2019
      • March 24, 2019
      • March 31, 2019
      • April 7, 2019
      • April 14, 2019
      • April 21, 2019
      • April 28, 2019
      • May 5, 2019
      • May 12, 2019
      • May 19, 2019
      • May 27, 2019
      • June 3, 2019
      • June 9, 2019
      • June 23, 2019
      • June 30, 2019
      • July 8, 2019
      • July 15, 2019
      • July 22, 2019
      • July 29, 2019
      • August 5, 2019
      • August 12, 2019
      • August 19, 2019
      • August 26, 2019
      • September 3, 2019
      • September 9, 2019
      • September 16, 2019
      • September 23, 2019
      • September 30, 2019
      • October 7. 2019
      • October 14, 2019
      • October 21, 2019
      • October 28, 2019
      • November 4, 2019
      • November 11, 2019
      • November 18, 2019
      • November 25, 2019
      • December 2, 2019
      • December 9, 2019
      • December 16, 2010
      • December 23, 2019
      • December 31, 2019
    • 2020 >
      • January 13, 2020
      • January 20, 2020
      • January 27, 2020
      • February 3, 2020
      • February 10, 2020
      • February 17, 2020
      • February 24, 2020
      • March 2, 2020
      • March 9, 2020
      • March 30, 2020
      • Special Message to Community
      • April 6, 2020
      • April 13, 2020
      • April 20, 2020
      • May 4, 2020
      • May 11, 2020
      • June 1, 2020
      • June 15, 2020
      • June 30, 2020
      • August 5, 2020
      • August 24, 2020
      • October 12, 2020
      • October 26, 2020
      • November 9, 2020
      • November 30, 2020
      • December 14, 2020
    • 2021

Echoes from Cañon

Board of Education to Consider Facilities Options

PictureCañon City Middle School is a historically significant building in our community. However, the main structure, built in 1925, is difficult o maintain and no longer fully meets modern instructional needs.
The Cañon City School District board of education is seriously considering 5 proposals to address much needed facilities upgrades.

Because of age (four of the district 's eight school buildings were constructed at least 65 years ago), the need to address pressing structural issues, worn roofing, and outdated water delivery systems, we have engaged the community about how we might best address the challenges we face in improving our facilities. 

One of our hopes is to secure significant grant dollars through Colorado’s Building Excellent Schools Today program to minimize the financial impact a comprehensive facilities solution would have on taxpayers.  This could allow us to address many outstanding issues for as little as 35 cents on the dollar.  However, competing for such a grant will require us to reduce our total building capacity because BEST will not pay for the improvement of facilities that are not being fully utilized by a school district.

Based on our facilities master plan, updated in January of 2016, we have identified needs for health and safety improvements totaling 14 million dollars.  The breakouts of these costs by building are as follows:​

Lincoln School of Science and Technology: Replacing exterior doors, windows and sidelights, replacing the water distribution system, refurbishing restrooms, and increasing the safety of the entry for approximately $680,000.  

McKinley Elementary: Replacing exterior doors, and windows, replacing the water distribution system, installing a new intercom system, refurbishing restrooms, and increasing the safety of the entry for approximately $1,000,000.  

Cañon Exploratory School: Installing a new fire alarm and intercom system, removing an asbestos-laden modular, and increasing the safety of the entry for approximately $425,000.

Cañon City High School: Replacing exterior doors and windows in older sections, upgrading HVAC systems, repairing roofs, replacing the water distribution system, refurbishing restrooms, conducting general ADA upgrades, and increasing the safety of the entry for approximately $4,700,000.

Harrison K-8: Increasing the safety of the main entry and installing a panic alarm system for approximately $350,000.

Washington Elementary School: Replacing exterior doors and windows, repairing structural deficiencies, replacing the water distribution system, removing an asbestos laden portable structure, and increasing the safety of the entry for approximately $3,200,000.

Cañon City Middle School: Adding cooling to the auditorium, installing ADA required upgrades, replacing heating and steam lines, replacing asbestos flooring and ceilings, repairing roofing, and increasing the safety of the entry at Cañon City Middle School for approximately $2,500,000.

ACCESS Center (which houses our Early Childhood Center, Cañon Online Academy, and Choice Points Alternative School): Replacing exterior doors and windows, upgrading the HVAC system, repairing roofs, replacing the water distribution system, and increasing the safety of the entry for approximately $950,000. 
​
Community members know Washington Elementary School has been a focus of discussion.  This is because structural issues were identified in the building last spring that would cost roughly 3.5 million dollars to fully address.  Because of this we have identified two potential courses of action, one in which we keep the Washington learning community where it is, and one in which we move that learning community to a different site within the district.

Two Options Being Considered to Maintain the Washington Learning Community

PictureWashington Elementary has been a focus of discussion because of structural issues identified last spring.
  • Option A calls for identifying facility space throughout the district that could be eliminated in an effort to get our total square footage in line with the requirements needed to qualify for a BEST grant, and to then apply for a number of grants that would allow the district to address the 14 million dollars in health and safety upgrades needed. The total cost for this option would be just under 17 million dollars.  This would include dollars designated for demolishing the old vocational facility at CCMS, as well as funds to make improvements to other parts of the CCMS building to absorb programs that currently utilize the old vocational facility.  We estimate the total cost to district taxpayers for these projects outlined to be just under 6 million dollars if we can secure a BEST grant.  The end result of this effort would be accomplishing the basic health and safety upgrades needed for all our current buildings, keeping the Washington learning community intact where it is currently located, while also reducing the square footage the district must maintain and operate on a yearly basis.
​
  • Option B also calls for identifying facility space throughout the district that could be eliminated in an effort to get our total square footage in line with the requirements needed to qualify for a BEST grant, and to then apply for a number of grants that would allow the district to address 12 million dollars in health and safety upgrades needed to buildings (this would be less because we would eliminate costs related to upgrading the current Washington building), while also providing for the construction of a brand new elementary school on the current Washington campus. The total cost of this option would be just under 27 million dollars. This would include dollars designated for a brand new 15 million dollar elementary school, demolishing the old vocational facility at CCMS, and for making improvements to other parts of the current CCMS building to absorb programs that currently utilize the old vocational facility.  We estimate the total cost of this plan to CCSD taxpayers would be just under 9.5 million dollars if a BEST grant could be secured to help fund it. The end result of this effort would be providing the basic health and safety upgrades needed for all current buildings and constructing a brand new Washington school where it is currently located, while also reducing the square footage the district must maintain and operate on a yearly basis.
​
The three options we are considering that would result in moving the Washington learning community to a different site are as follows:

Three of Our Options Would Relocate the Washington Learning Community

PictureOne consideration toward removing excess square footage in the district to increase chances of qualifying for a grant is demolishing the old vocational structure at CCMS and moving programs located in this building to the main CCMS structure.
  • Option C calls for moving the Washington school community over to the Harrison facility, moving current Harrison grade 6-8 students to the CCMS campus, demolishing the old Washington school and turning that property into field space to be utilized by high school soccer and softball programs, upgrading the current CCMS building to effectively house more than 700 middle school students, and providing other needed health and safety upgrades to all other remaining facilities.  The total cost of this option would be a little over 22 million dollars.  This would include funds designated for CCMS upgrades, demolishing the Washington facility, and improving that property. We estimate the total cost of this plan to CCSD taxpayers would be just under 8 million dollars if a BEST grant could be secured to help fund it.  The end result of this effort would be the creation of a large elementary school community on the Harrison campus, the establishment of a large middle school community on the CCMS campus, accomplishing the basic health and safety upgrades needed for all other buildings, while also significantly reducing the square footage the district must maintain and operate on a yearly basis.
  • Option D also calls for moving the Washington school community over to the Harrison facility, moving current Harrison grade 6-8 students to the CCMS campus, demolishing the old Washington school and turning that property into field space to be utilized by high school soccer and softball programs, and demolishing or repurposing the current CCMS building while constructing a new grade 6-8 facility to effectively serve more than 700 middle school students.  This would also provide needed health and safety upgrades to all other remaining facilities.  The total cost of this option would be a little over 40 million dollars.  This would include funds designated for a brand new CCMS building, and demolishing the Washington facility and improving that property.  We estimate the final cost of this plan to CCSD taxpayers to be just over 14 million dollars if a BEST grant could be secured to help fund it.  The end result of this effort would be the creation of a large elementary school community on the Harrison campus, the establishment of a large middle school community in a brand new facility on the CCMS campus, accomplishing the basic health and safety upgrades needed for all other buildings, while significantly reducing the square footage the district must operate on a yearly basis by eliminating two of its oldest and most expensive to maintain facilities.
  • Option E calls for moving the CCMS school community over to the Harrison facility, then moving some current Harrison grade K-5 students to McKinley, while also building a brand new 500 student Washington Elementary building on the CCMS grounds.  This would also result in the demolition of the old Washington school and turning that property into field space to be utilized by high school soccer and softball programs.  This option would also provide needed health and safety upgrades to all other remaining facilities.  The total cost of this option would be a little over 30 million dollars and would include funds designated for a brand new Washington building and demolition of parts, or all, of the current CCMS facility.  We estimate the total cost of this plan to CCSD taxpayers would be just over 10.5 million dollars if a BEST grant could be secured to help fund it.  The end result of this effort would be the creation of a large elementary school community on the CCMS campus, the establishment of a large middle school community in the Harrison facility, more efficient utilization of the McKinley campus, accomplishing the basic health and safety upgrades needed for all other buildings, while significantly reducing the square footage the district must maintain and operate on a yearly basis by eliminating 2 of its oldest and most expensive to maintain facilities.

Let's Review These Options

A quick review of the cost of these options to the community, if a BEST grant can be secured, is as follows:
  • Option A: Remove square footage and provide basic upgrades:  5.93 Million
  • Option B:  Remove space and replace current Washington school on current site:  9.44 Million
  • Option C:  Demolish Washington for field space, create a large elementary at Harrison and large middle school at CCMS, provide basic upgrades to all other buildings:  7.73 Million
  • Option D:  Demolish Washington for field space, create a large elementary at Harrison and build a  new large middle school at CCMS property, provide basic upgrades to all other buildings: 14.01 Million
  • Option E:  Demolish Washington for field space, all middle school students move to Harrison, and a new larger Washington is built on current CCMS site. 10.51 Million

What's Next?

Picture
Our board of education plans to consider these options at its work session on Monday, September 26th, and to whittle them down to two finalists for consideration.  The board will then hold a public hearing on those final options on Monday, October 10th, with the idea of deciding on a final course of action at its October 26th meeting.  This would allow the district's administration team the time needed to submit a competitive BEST grant with highly accurate cost projections by the end of February, 2017. 

We will find out if our grant has been awarded by June 1st, 2017 and if so, the board would then need to place a bond question on the November 2017 ballot to provide matching funds needed to execute the grant.  If the match is approved by the community, construction would take place from January 2018 through July 2019, with all schools operating as they currently are until the first day of school in August of 2019.  

If you would like to let our board members know which two of the current five options being considered you would most support, please feel free to contact them by email at the following addresses:

Larry Oddo:  oddol@canoncityschools.org
Lloyd Harwood:  harwoodl@canoncityschools.org
Mary-Kay Evans:  evansm@canoncityschools.org
Shad Johnson:  johnsos@canoncityschools.org
Kristyn Econome:  economk@canoncityschools.org

​George S. Welsh

Powered by Create your own unique website with customizable templates.